By Mike Lednovich
The long-anticipated opening of Alachua Street to Front Street has met yet another bump in the road, this time escalating construction costs.
A crucial stormwater capture and release system into the Amelia River was originally priced at $1.9 million in 2018.
But Fernandina Beach Interim City Manager Charlie George reported that the current estimate now stands at $7.3 million and the city does not have the money to fully fund the project.
"I've aged on this one," George told members of the Community Redevelopment Agency Advisory Board (CRAAB) Wednesday. "There's been a lot of angst over that (the project)."
Businesses along the Alachua Street and North Second Street corridor have put renovation and development plans on hold while waiting for what is designated as the Area 5 stormwater project to be completed.
Currently, Alachua Street is a dead end at the railroad tracks when driving west towards the river.
City officials maintain opening the Alachua Street crossing will provide for better traffic circulation (both vehicular and pedestrian) and support the economic redevelopment of several properties within the area of North Front Street, Alachua Street and North Second Street.
The project was originally scheduled to be completed last July.
George walked CRAAB members through the history of the project:
"We're going back to grants to try to meet that price ($7.3 million). I don't know if the $7.3 million is the actual number because we just went out to that one guy (CDC), so we'll put the whole thing out for competitive bid."
George said the city has the original $1.4 million budgeted for the project, as well as funding from other projects like $818,000 from ARPA funds to Area 5. That would fund a revised plan to get the road work, curbs, sidewalks and railroad crossing done to open the street, minus installation of the underground stormwater system. "We've got the money to finish this part of it, and our plan is to finish it by the end of the calendar year to get you up and running from a business standpoint," George said.
George said the road design for connecting Alachua to Front Street is done. "The railroad is going to put in the crossings and do the paving across the railroad tracks," he said.
The original project entailed the construction of the underground stormwater collection and treatment system first, to which area properties would be permitted to purchase “stormwater capacity” instead of requiring such treatment on each site. Once the stormwater improvements were completed, under the original plan, construction of the road, including sidewalks and streetscape, and a new railroad crossing could begin.
George said the new plan has been re-engineered and revised.