Dredging continues in south basin of city marina

Posted

Submitted by Suanne Z. Thamm

Reporter - News Analyst

April 8, 2019

Dredgng operations in the city marina's south basin are more than 80 percent completed.  Replacement docks for the southern attenuator are under construction.  With the 408 process (permit) for the northern attenuator now approved by the Army Corps of Engineers, the city is coordinating with FEMA to review the design and the $2,750,000 cost estimate.