Beach Renourishment Project update

Posted

Information and photos provided by

Vice Mayor Len Kreger

February 19, 2018 2:00 p.m.

The dredge is operating off shore, and estimated time to begin beach pumping is 1 March 2018. New Youk Avenue will be the start of the project area. Pumping will be completed 31 March 2018. Demobilization estimated completion on 14 April 2018.

Pipe in place on beach from Fort Clinch Jetty to Main Beach. Pipe will be extended from Dolphin to New York Avenue this weekend.

A typical walk through for beach access..

.