FERNANDINA BEACH - Nassau County should allow data centers under strict new regulations while eliminating their eligibility for county economic development incentives and property tax abatements, according to a 66-page draft report released Wednesday by a county fact-finding committee.
The committee also recommends monitoring facilities after construction, requiring regular reports on water and electricity consumption, and establishing procedures to address violations and the eventual closure of facilities.
The proposals are advisory. County commissioners have not yet reviewed or adopted the recommended regulations.
The first workshop will be held Monday, Oct. 26, from 3 to 5 p.m. in the Board of County Commissioners chambers in Yulee. A second workshop is scheduled for Nov. 9 at the same time and location.
The report follows months of public controversy over the prospect of large data centers coming to Nassau County, particularly facilities designed to support artificial intelligence and other computing operations that can consume enormous amounts of electricity and require substantial infrastructure.
The five-member committee, composed of county staff with expertise in planning, government finance, engineering, conservation and economic development, reviewed public testimony, research, presentations from industry and environmental representatives, and examples from other communities.
The committee recommends establishing classifications for different types of data centers rather than regulating small facilities and massive computing campuses under identical rules.
The county would establish a zoning compatibility table specifying where different classes of data centers could be permitted, along with standards governing building size, setbacks, landscaping, parking, screening and conservation easements.
The recommendations do not establish a universal minimum distance between data centers and residential neighborhoods.
The committee also proposes updating the county's Vision 2050 growth scenario map to account for data centers and associated infrastructure.

The report acknowledges that cooling technology can substantially affect water consumption. Evaporative cooling generally uses more water but less electricity, while closed-loop systems can reduce water consumption at the expense of increased electrical demand.
The report does not recommend that Nassau County assume water permitting responsibilities already assigned to the St. Johns River Water Management District. Instead, it calls for coordination with agencies that have regulatory authority.
The committee recommends developing measurable limits using both dBA and dBC sound measurements to address conventional and low-frequency noise.
Those restrictions would be accompanied by monitoring requirements and procedures for documenting violations, requiring corrective action and applying available enforcement measures.
The report calls for replacing County Resolution 2026-013 to exclude data centers from consideration under the Economic Development Grant Program and make them ineligible for county economic development incentives.
The proposed restrictions would apply to incentives controlled by Nassau County. They would not automatically eliminate incentives authorized or administered by the state.
The report calls for developers to bear the infrastructure costs associated with their projects rather than shifting those expenses to taxpayers or existing utility customers.
The report cites Florida's new data center legislation, Senate Bill 484, which established additional requirements for large facilities and protections intended to prevent certain electrical infrastructure costs from being passed to existing customers.
In Loudoun County, Virginia, data centers account for 45% of the county's general fund revenue while occupying approximately 3% of its land area, according to figures presented to the committee by consultant Molly Novotny, who has experience working in that county.
Those benefits, the committee concluded, must be evaluated alongside infrastructure demands, resource consumption and environmental costs.

According to the report, committee members could not distinguish outdoor noise from the facility from surrounding ambient noise. The facility operates in an existing telecommunications building, illustrating how location and design can limit impacts on surrounding properties.
The examples illustrate why the committee recommends regulating data centers according to their size, design, location and operating characteristics rather than imposing identical requirements on every facility.
The proposed regulatory framework would extend beyond the initial approval and construction of a data center.
Facilities would also need emergency response preparedness reports identifying hazards, emergency procedures and coordination with local emergency agencies.
The committee recommends establishing procedures for documenting violations, requiring corrective action and applying enforcement measures authorized by law.
That requirement responds to residents' concerns about what would happen if rapidly changing technology made large computing facilities obsolete.
The committee also acknowledges that poorly planned or operated data centers have caused problems in other communities.
Some residents urged the county to extend its moratorium for additional study. Others questioned whether Nassau County should impose regulations beyond existing state and federal requirements.
The report also cautions that changing development regulations could expose the county to legal challenges involving existing property rights, including potential claims under Florida's Bert J. Harris Jr. Private Property Rights Protection Act.
Residents may submit written comments through the county's Data Centers website at https://www.nassaucountyfl.com/1528/Data-Centers until Jan. 8, 2027, at 11:59 p.m.
County Commissioners will determine whether to adopt the committee's proposed regulatory approach, revise its recommendations or pursue a different policy as the county moves through the public hearing process.
The committee was established by the County Commission under Resolution 2026-102 to examine the potential impacts of data center development, hear public testimony, consult subject-matter experts and recommend regulations. County Attorney Denise May, Operations Manager Amy Bell and the Northeast Florida Regional Council provided additional support. The committee's recommendations are advisory, with final decisions on zoning, development restrictions and economic incentives resting with the County Commission.